DIRECTIONS
FOR AGENCY "FED PLAN" (A-106) INPUT FORM
ENVIRONMENTAL COMPLIANCE
PROGRAM NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION U.S. DEPARTMENT
OF COMMERCE
DIRECTIONS FOR:
AGENCY "FED PLAN" (A-106) INPUT FORM FEDERAL AGENCY ENVIRONMENTAL
MANAGEMENT PROGRAM PLANNING - PROJECT REPORT
Office of Procurement,
Grants, and Administrative Services Construction Staff
April 3, 1997
The following is a set of directions
for completing the "Agency 'Fed Plan' (A-106) Input Form: Federal
Agency Environmental Management Program Planning - Project Report" (
or "Fed Plan Input Form" for short):
I. Facilities/Installation
Information
- "GSA Installation #"
- Call Ms. Karen L. Ryscavage
at 202-482-1770 for GSA installation number.
- If there is no GSA installation
number, then use "X" followed by the last four digits
of the RSMIS facility code.
- "Ownership Type"
See page 3-6 of Federal Agency Environmental Management Program Planning
Guidance
- "EPA Region"
See Appendix H of Federal Agency Environmental Management Program Planning
Guidance
- "Name of Facility"
- 1st indicate the acronym
of the Line Office (or Staff Office)
- 2nd give the "Field
Office Designation" as identified in Field Office Locations
Worldwide: A DOC Handbook.
- "L/L Method"
See page 3-3 of Federal Agency Environmental Management Program Planning
Guidance
II. Project Information
- "Operable Unit/ADS Number" Do
not fill in.
- "Multiple Installations" Do
not fill in.
- "Project Milestones (month/year)" All
date are numbers; e.g., May 1998 is "05 1998".
- "Progress Code" See
page 3-8 of Federal Agency Environmental Management Program Planning
Guidance
- "Reason for Discontinuance" See
page 3-10 of Federal Agency Environmental Management Program Planning
Guidance
III. Funding Information
- "Federal Agency Funding
Account Code" Do not fill in.
- "Type of Cost" See
page 3-11 of Federal Agency Environmental Management Program Planning
Guidance
- "Funding Expected" Do
not fill in.
IV. Project Characterization
- "Law/Regulation/Executive
Order"
See Appendix A (Part 2) of Federal Agency Environmental Management Program
Planning Guidance
- "Environmental Category
(ECAT)"
Use "code" given in Appendix A (Part 2) of Federal Agency Environmental
Management Program Planning Guidance
- "Priority Score"
Do not fill in.
- "Compliance Status"
See page 3-15 of Federal Agency Environmental Management Program Planning
Guidance
- "Compliance Class"
See page 2-12 of Federal Agency Environmental Management Program Planning
Guidance
- "Geographic Initiative"
Do not fill in.
- "2. P2 Estimate"
See page 3-16 of Federal Agency Environmental Management Program Planning
Guidance
- "3. P2 Category (P2CAT)"
See Appendix B of Federal Agency Environmental Management Program Planning
Guidance
- "Reason for Initiation"
Optional, see page 3-17 of Federal Agency Environmental Management Program
Planning Guidance
- "Local Priority"
ASC priority using "Internal Program Policy: NOAA Pollution Control
and Treatment Project Prioritization Scheme" based on factor listed
in Appendix C of Federal Agency Environmental Management Program Planning
Guidance
- "Bureau/MACOM Priority" Do
not fill in.
- "Major Program Area"
Use one of the following:
"1" for compliance
"2" for pollution prevention
"3" for cleanup
"4" for conservation
(See page 3-16 of Federal Agency Environmental Management Program Planning
Guidance)
V. Project Narrative
- "Description" See
page 3-18 of Federal Agency Environmental Management Program Planning
Guidance. The description is the justification for the project's
priority, thus a weak description could result in a lower priority.
The description must include:
- Financial Statement requirements:
- If Liability, type
(that is: probable, reasonably possible, or remote)
- If costs cannot
be determined, state the following statement must appear
in the narrative: "costs cannot be calculated"
- NOAA Compliance Program
requirements:
- Provide EPA Audit Protocol
number and Regulatory Area requiring corrective action
- Provide specific Statutory
or Regulatory citation requiring corrective action
- A description of the
legal requirements
- The pollutant to be controlled
by the project
- A concise statement of
the problem
- The specific objective
of the program, project, or activity
- Additional rationale
for the project
|