NOAA Environmental Project
Management Policy
September 30, 1997
Revised September 30, 1998
NOAA Environmental Compliance Policy 97-02
1.0 Policy
1.1 In order to maintain uniformity throughout the National Oceanic
and Atmospheric Administration's (NOAA) environmental compliance offices
and to comply with applicable laws and regulations, the NOAA Environmental
Compliance Staff (ECS) in headquarters will maintain a master project
database which will include all environmental compliance projects required
by NOAA facilities.
1.2 The NOAA master project database will include synoptic information
and priority rankings for all NOAA environmental compliance projects.
It will support the development of the environmental compliance portion
of NOAA's budgets, spending plans, and annual financial statements.
1.3 Electronic methods will be used to maximum extent possible in maintaining,
sharing, and transferring the master project database.
1.4 New and updated Federal agency FEDPLAN submissions are due at EPA
Headquarters on September 1st of each year. NOAA is committed to providing
a timely submission of its project data.
2.0 Definitions
2.1 Environmental cost estimates within NOAA will be determined using
direct methods whenever possible, and through indirect methods when necessary.
2.1.1 Direct methods will be used according to the following order of
preference:
- Solicited estimates from reputable vendors or contractors for specific
or grouped activities
- Approved NOAA cost-estimating software (RACER or COSTPRO)
- Detailed "bottom-up" estimates
of the amount of labor, equipment, and materials and their associated
unit costs.
- Standardized published
references (such as "Means").
2.1.2 Indirect methods rely on the expertise of the estimator and extrapolation
from analogous data.
2.1.3 A simple statement will accompany the cost estimate stating why
the particular technique used was considered preferable.
2.2 Discovery as used in this document shall be defined as the date
that the government accepts the results of an observation, survey, audit,
or inspection. Acceptance can be agreement with preliminary results as
being indisputable. The receipt of a final survey, audit, or inspection
report will always constitute discovery if the government has not previously
agreed to preliminary results.
2.3 NOAA considers a project complete from an financial environmental
liability perspective when the work has been completed and the receipt
of contracted goods or services has been certified for payment.
2.4 Under Executive Order 12088, Federal agencies are required to submit
environmental plans to the Environmental Protection Agency (EPA) which
reviews and analyzes the plans and then forwards the analysis to the
Office of Management and Budget. The process of submitting, reviewing,
and analyzing agency plans is referred to as the FEDPLAN process (previously
referred to as the A-106 process). The primary objective of FEDPLAN is
to provide a mechanism for characterizing environmental activities, establishing
priorities, and identifying the resources needed to sustain compliance
with environmental requirements. At a minimum, NOAA prepares FEDPLAN
forms for all projects contained in its master database, with the exception
of any ship-related projects. Consistent with the practice of other Federal
maritime agencies, ships are not considered facilities and are not reported
in the FEDPLAN process. Projects which will be completed during the fiscal
year and will not continue in to the next fiscal year need not have a
FEDPLAN form prepared and submitted. Activities which occur on a regular
basis such as training and waste disposal are not included on the master
database and do not require submission of a FEDPLAN form.
3.0 Background
3.1 Discovery: NOAA environmental compliance projects are discovered
by various means, including environmental site audits, environmental
surveys, self inspections, external inspections, regulatory inspections,
and informal observations. Regardless of how a project is identified,
it is important that it be considered for inclusion in the NOAA master
project database.
3.2 Prompt Corrective Action: Some environmental compliance projects
either have no associated cost or can be corrected with available funding.
Such projects should be completed promptly and do not require further
action. However, many projects either cannot be funded immediately or
must be funded from a source other than the facility at which the project
exists. These projects must be documented and entered into the master
project database, regardless of the funding source or the fiscal year
of anticipated funding.
3.3 Examples:
3.3.1 Attachment 1 outlines the timing, actions, and products at each
level of responsibility within NOAA necessary to support the master project
database.
3.3.2 Attachment 2 presents an example of the NOAA process.
4.0 Procedures
4.1 Line Office Role:
4.1.1 The process
begins with the completion of a "Project Prospectus
Sheet" (see Attachment 3) by the Line Office representative (as
designated). This form should be completed within 30 days of "discovery" of
an unfunded environmental project. The Project Prospectus Sheet form
is available on NOAA's environmental compliance web site.
4.1.2 The Line Office representative should estimate the cost of the
project, indicate the rationale supporting the estimate, and include
it on the Project Prospectus Sheet.
4.1.3 The Project Prospectus Sheet is submitted to the facility's Regional
Environmental Compliance Officer (RECO).
4.2 RECO Role:
4.2.1 Within 30 days of receiving a Project Prospectus Sheet, a RECO
will validate the project described as a legitimate environmental compliance
project and insure that an appropriate cost estimate is attached to the
project.
4.2.2 The RECO will determine if the project imposes a financial environmental
liability on NOAA (see Attachment 4).
4.2.3 Project Prospectus Sheets, cost estimates, and other data pertinent
to a particular facility's environmental compliance projects will be
maintained by the RECO in project files. A form similar to the Project
Validation Checklist (see Attachment 7) is recommended for attachment
to the front cover of the file to track quarterly (see paragraph 4.5)
and semiannual (see paragraph 4.6) reviews.
4.2.4 All projects determined to be financial environmental liabilities
shall be subject to the criteria specified on the Environmental Project
Liability Checklist (see Attachment 5). The checklist shall be completed
by the RECO for each project and maintained with the data specific to
that project. All financial environmental liability project files shall
be distinctively marked to facilitate ease of identification.
4.2.5 All environmental project data will then be summarized and submitted
by the RECO to the ECS headquarters (HQ) for inclusion in the master
project list database.
4.2.6 Simultaneous
with the development and submission of the Project Prospectus Sheet,
the RECO
will complete and submit a FEDPLAN form. NOAA
uses its internal directions for "Agency A-106 Input Form, Federal
Agency Environmental Management, Program Planning - Project Report" dated
August 22, 1995, and revised August 5, 1996, for completing the FEDPLAN
forms. Additional information is available in EPA 300-B-95-001, "Federal
Agency Environmental Management Program Planning Guidance," dated
October 1994.
4.3 Headquarters (HQ) Role:
4.3.1 HQ will maintain NOAA's master project database. Attachment 6
describes the contents of the project database.
4.3.2 HQ will validate project and FEDPLAN submissions by reviewing
the submitted data for complete entry. The submitted project will be
compared to other projects submitted for the same facility to ensure
that it represents work not previously described.
4.3.3 HQ will assign project numbers to all validated submissions and
update the master project database accordingly.
4.3.4 HQ will be responsible for coordinating complete reconciliation
of the master project database and any lists, files, or other information
held in the field, and for using the project data in supporting the annual
budget submission
4.4 Exceptions:
4.4.1 Health or Safety
Threats: If a "discovered" environmental
project presents an immediate threat to the health or safety of individuals
or to the environment, the process of Project Prospectus Sheet preparation,
cost estimate preparation, project validation, and entry onto NOAA's
master project list database shall be expedited such that the entire
process is completed in less than 15 days.
4.4.2 End-of-Year Discoveries:
4.4.2.1 During the
last 60 days of the fiscal year, any "discovery" of
an unfunded environmental project shall be considered for its possible
inclusion as a financial environmental liability.
4.4.2.2 If the project is determined to be a financial environmental
liability, a cost estimate will be prepared to determine if it exceeds
the NOAA threshold for accrual.
4.4.2.3 If the financial environmental liability exceeds the NOAA threshold
for accrual, the process of Project Prospectus Sheet preparation, cost
estimate preparation, project validation, and entry onto NOAA's master
project list database shall be expedited such that any project qualifying
for accrual on the annual NOAA Financial Statement prior to the last
15 days of the fiscal year shall be recognized and properly reported.
4.5 Quarterly Reviews:
4.5.1 Once a project has been included in NOAA's master project database
of environmental projects, Line Office representatives should review
those projects applicable to their facility on a quarterly basis. This
review will validate that those projects are still required and that
their scope remains accurately presented.
4.5.2 The appropriate RECO will coordinate and assist in this review
and validation.
4.5.3 Each RECO will review and update the project list and FEDPLAN
forms for all projects designated for his or her region of responsibility
and forward the results of that review to HQ.
4.6 Semiannual Reviews:
4.6.1 On a semiannual basis, the RECOs will similarly review and validate
the cost estimates and forward the results to HQ. For those estimates
where there is no change, the RECO shall initial and date the verified
cost estimate.
4.6.2 The project list validations of paragraphs 4.4.3 and 4.5.1 will
become part of the HQ-coordinated master project database reconciliation
discussed in paragraph 4.3.3.
4.7 Project Removal or Reduction:
4.7.1 A project is recommended for removal from the master project database
when the work has been completed and the receipt of contracted goods
or services has been certified for payment.
4.7.1.1 For financial environmental liabilities:
4.7.1.1.1 The RECO shall make this recommendation to headquarters immediately
upon meeting the criteria of paragraph 4.7.1.
4.7.1.1.2 Recommendations for removal will be validated and completed
within 7 days of receipt at HQ.
4.7.1.2 For other than financial environmental liabilities (completion,
duplicate entry, overtaken by events, etc.), recommendations for removal
will be made by the RECO, validated at HQ, and entered on the master
project database no less than quarterly.
4.7.2 Large projects may be subject to payments for work progress and
may extend over many months or even years. Although such projects are
subject to the requirements of paragraph 4.7.1, the liability imposed
by these projects must be reduced periodically to reflect the progress
payments made.
4.7.2.1 For all environmental liabilities, progress payments shall be
reported by the RECO semiannually (in conjunction with cost estimate
verification, paragraph 4.6.1), validated at HQ, and entered on the master
project database.
4.7.2.2 The reduction of an environmental project's liability to reflect
progress payments shall be carefully coordinated with the servicing finance
office to insure that liabilities are not double counted.
4.7.2.2.1 The original liability estimate for a given project number
will be reduced by the sum of all accruals and disbursements related
to that project number during the reporting period.
4.7.2.2.2 Only the difference between the original liability estimate
and the total of the accruals or disbursements made shall be posted on
NOAA's annual financial statements.
4.7.2.3 Although reduction of the liability associated with an environmental
project prior to certification of successful completion by a regulating
agency runs a risk that such certification will not be forthcoming, this
risk is considered remote and not necessary for estimating.
4.8 Annual Processes:
4.8.1 At the end of each fiscal year, HQ will save and store the validated
and updated master database as a separate file for historic reference.
4.8.2 Also at the end of each fiscal year, HQ will transfer those projects
completed during the year to a separate database comprised only of completed
environmental compliance projects.
4.8.3 The validated and updated master database, having had the completed
projects removed, will form the initial master project database for the
new fiscal year.
4.8.4 At the end of each fiscal year, HQ will provide a summary of NOAA's
financial environmental liabilities to NOAA's Chief Financial Officer/Chief
Administrative Officer. Any disclosures necessary to clarify the financial
environmental liabilities will be coordinated by HQ.
4.8.5 The master database, as supplemented with information provided
by the RECOs, will be used to generate NOAA's annual FEDPLAN submission.
4.9 Database Protocol:
4.9.1 The master project database maintained by HQ is the only authorized
listing of NOAA environmental compliance projects.
4.9.2 Other specially tailored databases are permissible at the RECO
or Line Office designee level, but they MUST match exactly the environmental
projects contained on the master project database for that region or
facility.
4.9.3 Any differences in project listings must be either reconciled
for inclusion on or removal from the master project database, or removed
from or added to the tailored data base.
4.10 Control: The point of contact for the NOAA environmental project
management shall be the Deputy Chief, Environmental Compliance Staff.
|